The James City County Board of Supervisors has approved a $1.5 million contract to build the Warhill Skatepark. The contract was awarded to Spohn Ranch, Inc., moving the replacement for the county’s closed skate facility towards construction.
Alister Perkinson, assistant director of parks and recreation, told supervisors the new park will be “a vast improvement” over the previous skatepark near the recreation center, which operated for close to 25 years before it closed. The new park will sit at Warhill Sports Complex, 4900 Stadium Road, according to Perkinson’s memo, in open space between the basketball courts and new fitness court and the multiuse turf fields, Perkinson said. It will cover, Perkinson said, a little under 18,000 square feet, including sidewalks, seating and shade, compared with close to 10,000 square feet for the old one.
James City County supervisors approved a $1.5 million contract to build the new Warhill Skatepark for skateboarders, rollerbladers and BMX riders.
Source: Spohn Ranch Skateparks / James City County
Perkinson said the design reflects feedback from more than 200 residents gathered during community engagement last fall. According to Perkinson’s memo, Spohn Ranch initially completed that engagement and the design. Residents, whether beginners or experienced skaters, did not want an expert-only park that only professionals could ride, he said, and that feedback was nearly universal. The park is “for all wheels,” he said, serving skateboarders, rollerbladers and BMX riders. Perkinson said the park combines street-style skating with ramps and bowls. Beginners can use it, he said, and more advanced riders will still find it rewarding.
The park has two levels, and many of the elevation considerations also involve stormwater drainage, Perkinson said. Building a deep bowl almost requires building up, he said, to get the drop needed to drain stormwater out of the area.
The site plan is approved, and the contract moves the project into construction, Perkinson said. Previously authorized Capital Improvement Program budget funds are available to fund the project, according to the resolution. Perkinson said staff hope to begin construction in November or December and are looking to finish this coming spring.